NAVY NEWS

JUST IN: Navy Working Through Columbia Submarine ‘Challenges' on Tight Schedule

11/12/2020
By Yasmin Tadjdeh
An artist rendering of the future Columbia-class ballistic missile submarine.

Navy conecept

The Navy is working through challenges with its Columbia-class ballistic missile submarine program as it tries to meet a tight delivery schedule for its next generation of nuclear-armed boats, said the commander of Naval Sea Systems Command Nov. 12

The project is the sea service's top modernization priority as it seeks to replace its aging Ohio-class subs. On Nov. 5, it awarded a $9.4 billion contract to General Dynamics Electric Boat for full construction of the lead ship and advanced procurement for the second vessel. The Pentagon plans to buy a total of 12 boats.

The Navy aims to have the first ship, USS Columbia, on patrol by 2031, and officials have said there is little margin for schedule slippage.

“The program is on plan,” said Vice Adm. William Galinis. However, “we are seeing … some challenges as we come through the final parts of the design and get into construction a little bit.”

This stage of the process is often where issues can spring up, he told reporters during a meeting hosted by George Washington University’s Project for Media and National Security.

For “new ship construction programs in general that's always kind of a challenge point … to get that design completed and get into construction,” he said. “And then you're building the first vessel and you're going to have production issues along the way. And then the next phase is when you start to activate the systems, bring the submarine online and then get it delivered to the fleet. So that will really be our next challenge.”

Galinis gave the two main shipbuilders involved with the program — General Dynamics Electric Boat and Huntington Ingalls Industries Newport News Shipbuilding — high marks for working with the program executive office to keep the project on schedule.

About 350 companies in the industrial base and supply chain are considered to be critical for the program, Galinis said. Among those, the Navy believes about 5 to 10 percent are “somewhat challenged” in one area or another to be able to meet the demand for the submarines, he noted.

“The supplier base is something that we continue to watch pretty closely,” he said. PEO Submarines “has done a pretty good job reaching out and working with their supply base through the shipyards to really kind of get a good understanding of where ... the risks are.”

Across the supplier base, the Navy is most concerned about welding and non-destructive testing skills.

“That’s a big part of shipbuilding — and that's not just for Columbia, that's sort of across the enterprise,” Galinis said. “I'm seeing some challenges there.”

The sea service is working to ensure it has enough electricians and mechanics to meet the demand, he said.

Writ large, the Navy’s biggest challenge is on-time delivery of ships and submarines, Galinis said. “We want them complete [and] we need the right level of quality,” he said. “That's both in new construction and repair.”

Maintenance, which the Navy has struggled to perform on time in recent years, is one of Galinis’ top focus areas. While more improvement is needed, he noted that the service is making progress.

Last year, the service conducted a study of its maintenance availabilities and found that it was not properly planning for availability duration, he said.

Following that analysis, the Navy “reset” the availability duration of its ships, a move which Galinis believes will help the service overcome issues.

From fiscal year 2019 to 2020, the service decreased the “days of maintenance delays” by over 80 percent, he said, from more than 7,000 to about 1,100. However, “we adjusted the duration of the availability in some cases, so we changed the baseline,” he added. That means that percentage decrease would actually be closer to 40 if the service went with its original baseline, he noted.

“Overall we absolutely made a significant improvement in FY ’20 compared to FY ’19,” Galinis said.

However, “going forward, what I would tell you is we're not going to get to zero [delays] in ’21," he added.

There are about half a dozen ships that will pose challenges, he noted, including some Aegis cruisers as they undergo extended maintenance for the service’s cruiser modification program.

About 67 percent of the Navy’s maintenance availabilities are tracking toward on-time delivery, he said.

“That’s up from less than 50 percent last year,” he said. “We’re moving the needle in the right direction, but there's still a lot of work to do there.”

Topics: Shipbuilding, Navy News

Comments (2)

Re: Navy Working Through Columbia Submarine ‘Challenges' on Tight Schedule

Hopefully Submarines will remain top priority. Been a while since they were.

GS at 9:57 AM
Re: Navy Working Through Columbia Submarine ‘Challenges' on Tight Schedule

I don't understand the following:
- Why don't we sub-out ship building and repair to other countries? Italy builds the highly sensitive and secret F-35, while Japan has built very technically sensitive wings for Boeing's jets for decades.
The new hulls of ships can be built, at a much lower cost, in foreign yards and could be fitted in the US yards.
Repairs to a great degree can be performed in foreign yards. One of our biggest repair facilities was Subic Bay in the Philippines, before we were asked to leave.
So in order to build out the fleet AND keep it in good repair, we need to use allies' capabilities.
- Why retire navy ships? Instead why not auction them to allies to bolster their fleets? If there are no takers, then retire them. Our ships outstrip those of most other nations and though they are considered eligible for retirement by the US navy, that is according to OUR requirements. Many, many other nations would LOVE to take on our ships, among them Vietnam, Taiwan, India, Japan, Australia, SK to name a few. Subs, carriers, destroyers, etc would increase the worlds security dramatically, including ours, if they are kept on station.

John Stevenson at 7:52 PM
Retype the CAPTCHA code from the image
Change the CAPTCHA codeSpeak the CAPTCHA code
 
Please enter the text displayed in the image.