|
FEATURE ARTICLE
February 2005
Army’s War-Weary Choppers Get Repairs
by Frank Colucci
To tackle a growing backlog of damaged
and worn-out helicopters, the U.S. Army’s aviation depots
and contractors are operating at full tilt.
By
early December, at least 464 helicopters back from Iraq and Afghanistan
had been returned to combat-ready status, in a process the Army
calls “reset.” More than 500 additional aircraft are
awaiting repairs.
The aviation reset project is now estimated to cost $1.2 billion
and requires a worldwide effort by the reset program office within
the Army Aviation and Missile Command (AMCOM).
“Our job is not to zero-time these aircraft as a depot would
do, but to put them back in mission-capable status in the hands
of the soldier,” said program manager Col. Ray Woolery.
Army helicopters were used heavily in the initial combat stages
of Operations Iraqi Freedom and Enduring Freedom. Brig. Gen. E.J.
Sinclair, commander of the Army Aviation Center at Fort Rucker,
Ala., pointed out that AH-64 Apaches, in the major combat phase
of Iraqi Freedom, decimated three divisions of Iraqi armor, while
UH-60 Black Hawks flew air assaults. In Afghanistan, CH-47 Chinooks
inserted special operations teams at mountain elevations up to 16,000
feet.
Ongoing stabilization operations in both theaters require aviation
units sustain high operational tempos. Individual OH-58D Kiowa Warriors
of the 1st Battalion, 4th Aviation Regiment have flown approximately
102 hours a month in Iraq. As of mid-October, the 21 Apaches deployed
in Afghanistan each were averaging 54 flight hours a month, which
is more than double typical peacetime use.
Battle damage and harsh environments have taken their toll on the
helicopter fleet. Most Apaches that were shot up in the much-publicized
strike on Karbala in Iraq returned to the fight after field repairs.
Maintainers in Iraqi Freedom removed 35 pounds of sand from under
a radio console in one Black Hawk. Rotor blades in the desert commonly
suffer significant sand erosion. Abrasive sand also clouds windshields,
and grains caked between panels by field washing ultimately cause
corrosion.
CH-47D Chinook cargo helicopters, especially, are showing signs
of age-induced wear. “We have found a number of our aircraft
that had significant sheet-metal requirements caused by high altitude,
high gross-weight flights,” observed Woolery.
Army ground and aviation equipment returning from combat rotations
goes through reset for repeat deployments. The AMCOM reset office
became operational in April 2003. By early December, contractors
and Army personnel had reset helicopters from both Iraq and Afghanistan
at 14 government facilities and one contractor site. At that time,
AMCOM had 225 aircraft in process. Woolery explained, “What
we’re trying to achieve is to bring these back to pre-deployment
condition.”
Some reset work is done by the aviation units themselves upon return
to their home bases. Commercial contracts are modeled on those used
by the Air Force to hire contractor field teams.
Workers from L3, Lear Siegler, DynCorp and DS2, a joint venture
of Lockheed Martin and the Day & Zimmermann Group, perform reset
work at sites near deploying units, including Forts Hood, Drum,
Knox, Polk, Campbell and Bragg in the continental United States.
DynCorp, for example, works on AH-64s and OH-58Ds in Temple, Texas,
near Fort Hood.
Additional reset sites have been added in Hawaii and Germany to
refurbish aircraft from the Hawaii Army National Guard and U.S.
Army Europe. “Any helicopter that says U.S. Army on the side
is getting the same treatment, whether it be Guard, Reserve or active-duty
component,” said Woolery.
The contractor teams must follow AMCOM technical manuals. Cost
estimates are adjusted, once aircraft are torn down. Aircraft marked
for reset are analyzed first by the owning unit in-theater, then
again when torn down at the worksite.
Most estimates have been revised downward, as of late. “The
initial aircraft that fought the war and came out took a lot more
work,” acknowledged Woolery. Stabilization operations are
more likely flown from concrete hardstands than open desert, and
give units more time to do maintenance. “We expect the next
lot to be in better shape. They have not had the [same] threat of
air defenses and small arms as the guys in the shooting part of
the war,” he noted.
Most tasks are like those done by Army aviation unit and intermediate
maintenance facilities. The duration of the work varies from one
aircraft to another, but average time is 69 days for the UH-60L,
74 days for the AH-64D and 122 days for the CH-47D. Corpus Christi
Army Aviation Depot still repairs aircraft with major crash or battle
damage, but it also fields depot teams to supervise more involved
repairs at reset sites.
AMCOM expects Boeing to reset more than 40 Apaches at its Williams
Gateway facility, southeast of the main Apache manufacturing and
modernization plant in Mesa, Ariz. Boeing has about 75 people committed
to reset work at the two facilities. The Williams Gateway site has
long been used for maintenance and modification of Army Apaches
in addition to repairs on Air Force T-38s and Navy F-18s. The first
of 10 AH-64As and five AH-64Ds covered by a firm fixed-price contract
was returned to the Army on Sept. 20.
With Apaches flying in at two- to three-week intervals, deliveries
under the initial contract will continue through July 2005. “These
aircraft are flying in because the guys in the field are doing a
fantastic job maintaining them,” noted John Guasto, Boeing
Apache reset program manager. “For what these things have
been through, they’re in great condition.”
The first AH-64A to be reset was a veteran of Iraq, Afghanistan
and Kosovo. It arrived with five or six bullet holes in the airframe
and one in the front cockpit canopy. Like most of the aircraft to
follow, the first Apache in reset suffered from sand intrusion.
“It had seen a lot of action, a lot of hard use,” said
Dan Anglim, Boeing director and general manager of aerospace support,
in Mesa. None of the Apaches returned to Mesa so far has been shot
up so badly that it warranted disassembly in manufacturing fixtures.
Though most of the returning aircraft have suffered erosion damage
on main and tail rotors, particularly around the rotor blade tip
caps, sand-related corrosion has been minor. “While they need
some work, they’re not basket cases,” explained Anglim.
The Apache reset process is divided into three 20-day “cells.”
Workers remove all access panels to wash away trapped sand. “We
do a massive cleaning,” said Guasto. “We take the aircraft
to the wash rack two to three times in the first 20 days just to
get all the sand off.”
The next 20 days are dedicated to a thorough inspection and repairs
in accordance with the standard Apache 500-hour, phase-four inspection.
“We repair everything possible to the Army technical manuals,”
explained Guasto. “If it’s possible to repair it, we
repair it.”
Boeing workers remove the main and tail rotors and all drive components
including the transmissions and driveshafts. They replace components
with less than 250 hours life remaining, and install new bearings
and seals. Detailed inspection often uncovers additional damage.
Temporary field repairs are removed and structures restored. “We
bring the aircraft as close to pre-deployment condition as possible,”
said Guasto.
Reset also provides an opportunity to incorporate engineering changes
authorized after the aircraft was built. For example, Apache tail
booms are strengthened and vertical stabilizer mounts are changed.
“The aircraft when it leaves is definitely in better condition
than when it was deployed,” Guasto mentioned.
The last 20 days at Mesa are devoted to delivery preparations including
electrical power-up, fuel pressurization and maintenance flights.
“We like to give them a clean log book without discrepancies,”
he said. The first reset AH-64A went to the Texas National Guard.
The 10 AH-64As covered by the first reset contract will remain part
of the Apache “legacy” fleet in the National Guard and
are not scheduled for AH-64D remanufacture. A-model Apaches earmarked
for D-model modernization will not go through the complete reset.
However, the Apache program manager will receive funds to pay Boeing
for repairs over and above the standard AH-64D conversion.
The company has applied lean manufacturing principles to the assembly
line. Segregated tools and parts are arrayed near workstations to
reduce cycle times. The reset objective for the AH-64A is 71 days.
Boeing completed the first aircraft in 58 days, the second in 62
days and the third in 65 days, company officials said.
AMCOM receives a report on all components that were replaced. It
also has a review mechanism in place to adjust expected component
lives and spare parts orders based on reset work. “We routinely
evaluate what we’re finding in reset, what we’re finding
in theater, to improve our technical manuals, inspection procedures
and all the management,” said Woolery.
Back To Top
|