ARTICLE
August 2003
Navy Struggles to Get Multiyear Funds for Va.-Class Submarines
by Geoff S. Fein
A General Accounting Office report is questioning whether unrealistic cost
estimates, inflation adjustments and competition among other Navy programs will
offset any savings from multiyear procurement for the Virginia-class submarine
program.
The report, released on June 23, raised concern about the Navy’s request
for advance funding for the submarine program.
The Navy is seeking advanced funding for seven Virginia-class submarines from
fiscal years 2004 through 2008. The Navy has sought congressional approval of
a multiyear procurement of $390 million in fiscal years 2004 and 2005 and $190
million in 2006. Navy officials claim this will allow the program to reduce
needed funding in future years.
But savings could be eroded if the program’s costs increase or substantial
design changes are needed. And competition among Navy programs could also affect
long-term savings, the report stated.
GAO points out the Navy cut $270 million in research, development, test and
evaluation funds from fiscal years 2004 through 2007, and an additional $40
million per submarine in technology insertion funds for the same time period.
The cuts were made to “help fund higher Navy priorities,” the report
states.
The cuts will impact such efforts as continued development of an information
assurance solution for the sonar and combat control networks, correction of
high priority deficiencies noted in the operational assessment of the non-propulsion
electronics systems, and evaluating causes and developing fixes for acoustic
performance deficiencies. Technology insertion also will be delayed for several
years, GAO said.
In addition, procurement savings over several years could be eroded as the
Navy continues to cut funding due to “defense-wide inflation adjustments,”
the report said. The Navy has already cut $600 million from the Virginia-class
procurement account and $2 million a year in RDT&E funding from 2004 to
2009.
According to GAO, the “program’s costs estimates have not proven
realistic.” Using the Navy’s own documents, GAO said costs on the
submarine have “exceeded baseline estimates by 24 percent.” That
included the potential savings from multiyear procurement funding, which has
yet to be authorized. Without the savings, cost overruns would have been 31
percent, GAO said.
Program officials revised the baseline estimate in April 2003. Contract negotiations
for the acquisition of additional ships raised further questions about the realism
of the Navy’s cost estimates. Program officials said the contractor’s
bid exceeded the Navy’s estimate by $1 billion. Officials reported that
a tentative agreement has been reached resulting in a price within the program’s
budget, but the Navy altered the scope of the contract to reach that price,
GAO reported.
“This experience with the program’s cost estimates raises questions
regarding the realism of potential savings estimates. Moreover, should costs
exceed estimates, the program would need additional funding or would have to
make additional tradeoffs to program scope,” GAO said.
Design changes are still likely, because the program is early in the acquisition
cycle, the report noted.
“The lead ship (SSN 774), which will be delivered in June 2004, will
undergo only a pier-side review of the total ship survivability trial and will
not undergo a full ship shock test. The second ship (SSN 775), is expected to
undergo both the total ship survivability trial and the full ship shock test
in 2006. These tests, as well as sea trials, are likely to identify necessary
design changes that may affect the components and materials already purchased
as well as the cost and schedule of the program,” GAO said.
The last shipbuilding program to get multiyear procurement contracts was the
Arleigh Burke-class (DDG-51) destroyer. It was well into its acquisition cycle
when authority for the multiyear procurement contract was approved, according
to the study.
Navy officials, however, dispute GAO claims about design and cost estimates.
Although officials conceded that several factors could affect savings, they
did not agree that the Navy gives priority to other programs over the submarine.
According to a Navy official, the Virginia-class submarine is “given priority
by the Navy when allocating planned resources.”
“GAO’s view fundamentally misunderstands the Virginia-class program
and Navy shipbuilding,” a Navy official said.
The Defense Department has accepted the Navy’s cost estimates. But GAO
says it does not believe the Navy’s numbers are reliable.
Navy officials also believe that the ship’s design is stable “based
on completion of 99.8 percent of the drawings and low engineering changes,”
the report said.
Navy officials said, in response to GAO claims, that improved design and modeling
technologies have diminished the risk of design changes.
But GAO said it’s reasonable to expect that changes to the design will
be necessary as a result of launching and testing of the first submarines.
“Design changes could erode expected savings,” GAO warned.